射阳港口电厂河段的整治及其工程效果

Regulation of Sheyang harbor power plant reach and its engineering effect

  • 摘要: 通过河床演变分析 ,指出了射阳港口电厂河段码头前沿淤积的原因 ,提出了整治原则与整治工程方案 .经过定床、动床河工模型试验 ,优化了整治工程方案 .工程实施两年后的河段地形与试验结果几乎一致 ,且整治效果十分明显

     

    Abstract: The siltation mechanism at the wharf apron of the river reach of the Sheyang harbor power plant is pointed out, and the regulation principle and the scheme are introduced through the analysis on the river evolution. The complex water sediment condition of this reach makes the simulation more difficulty. An optimum regulation scheme is suggested after by the fixed and moveable bed model tests. The regulation works completed for two years are in good agreement with the prediction by the model experiments.

     

/

返回文章
返回